The 10,000 billion VND flood-resistant project in Ho Chi Minh City officially restarted after 1 year of "projection"

Thursday, 28/02/2019, 09:48 (GMT+7)

The 10,000 billion VND flood-resistant project in Ho Chi Minh City officially restarted after 1 year of "projection"

On February 27, Trung Nam Co., Ltd BT 1547 (belonging to Trung Nam Group), the investor of the project to solve flooding caused by high tide in Ho Chi Minh City takes into account the climate change factor (stage 1). VND 10,000 billion said it officially restarted construction again after nearly a year of stagnation.

Dự án chống ngập 10.000 tỷ đồng tại TP.HCM chính thức tái khởi động trở lại sau 1 năm

 

Mr. Nguyen Tam Tien - Director of Trung Nam BT Company Limited 1547 said that the project has now completed 72% of the volume, the items have risen to the surface.

According to Mr. Tien, the main steel rust in the floating floor has been treated so the project still ensures stability and sustainability. Although the project stopped construction for a long time, it did not affect the construction quality.

Mr. Tien also said that since before the Lunar New Year, investors have restarted the project in the construction items of Ben Nghe, tide prevention sluice gates, Tan Thuan and Phu Dinh. Currently, investors start to restart all simultaneously in all construction items of the project.

Mr. Tien added that if Ho Chi Minh City handed over the site in June, Trung Nam would try to complete the entire flood-proofing project at the end of 2019 or at least put it into operation in the first quarter of 2020. Recently , TP has adjusted a number of routes to reduce the clearance compensation (land acquisition). Therefore, 97/238 households have been reduced to land acquisition.

"All problems, the recommendations of departments, agencies and investors have been solved by the City People's Committee. HCM City People's Committee has also approved the evaluation report of the supervision team to adjust the FS. (basic design) of the project, the City People's Committee will work with the State Bank and the Government to extend the funding period for the project after the June 30 deadline ... "Mr. Tien said.

And the processing of large quantities of iron and steel on the site rusted due to sun exposure to the sun for many months, Mr. Tien said, will cleanse the rust, ensure not affect the quality and durability of construction.

Earlier, the HCM City People's Committee instructed the relevant agencies to speed up the compensation for land clearance, agree to adjust the design of the project, the land acquisition boundary of the project as proposed by the Inspection Team to evaluate the project. in Report No. 693/2019.

Vice Chairman of Ho Chi Minh City People's Committee Tran Vinh Tuyen also approved to adjust the design of the embankment section of Ba Butterfly sewer, Phu Thuan Ward, District 7, at the request of the Department of Agriculture and Rural Development.

Ho Chi Minh City People's Committee also assigned the Department of Agriculture and Rural Development to assume the prime responsibility and coordinate with relevant units and project investors to quickly review and advise and propose the City People's Committee to approve the adjustment of the boundary. project for approved positions and category of Butterfly Lady's sewage before March 5.

Besides, Ho Chi Minh City People's Committee also approved the policy of hiring a consultancy unit which is the Mechanical Research Institute under the Ministry of Industry and Trade to verify and evaluate the change of steel materials (steel grade) to manufacture project gate valves as intended. opinions of the Ministry of Agriculture and Rural Development. These moves of the HCM City People's Committee are considered to remove problems for the project.

Project against flooding in TP. Ho Chi Minh City considers climate factors (phase 1) including all 6 projects: Ben Nghe, Manh Cay, Muong Slu, Phu Dinh, Phu Xuan and Tan Thuan sluices, started in June. / 2016.

In addition, the project also has a section of dyke along Saigon river (from Vam Thuat to Song Kinh) with the length of 7.8km, protecting the vital sections, small culverts under the dike with aperture of 1-10m.

After completion, the first flood protection project in Vietnam is expected to address flooding due to rain and high tide for an area of ​​570km2 with about 6.5 million people in the project area.

 

Nam Phong